A) Yes, because the IRR is 10.75 percent
B) Yes, because the IRR is 12.74 percent
C) No, because the IRR is 10.75 percent
D) No, because the IRR is 12.74 percent
E) The answer cannot be determined as there are multiple IRRs
Correct Answer
verified
Multiple Choice
A) measures profitability rather than cash flow.
B) discounts all values to today's dollars.
C) is expressed as a percentage of an investment's current market value.
D) will equal the required return when the net present value equals zero.
E) is used more often by CFOs than the internal rate of return.
Correct Answer
verified
Multiple Choice
A) produce a positive annual cash flow.
B) produce a positive cash flow from assets.
C) offset its fixed expenses.
D) offset its total expenses.
E) recoup its initial cost.
Correct Answer
verified
Multiple Choice
A) duplication.
B) the net present value profile.
C) multiple rates of return.
D) the AAR problem.
E) the dual dilemma.
Correct Answer
verified
Multiple Choice
A) $2,861.62
B) $2,311.92
C) $2,900.15
D) $3,248.87
E) $3,545.60
Correct Answer
verified
Multiple Choice
A) A; B; A; A; B
B) A; A; B; B; A
C) A; A; B; B; B
D) B; A; B; A; A
E) B; A; B; B; A
Correct Answer
verified
Multiple Choice
A) never pay back.
B) have a negative net present value.
C) have a negative internal rate of return.
D) produce more cash inflows than outflows in today's dollars.
E) have an internal rate of return that equals the required return.
Correct Answer
verified
Multiple Choice
A) $0; -$665.07
B) $0; $6,916.59
C) $0; $7,208.19
D) $15,900; $7,208.19
E) $15,900; $6,916.59
Correct Answer
verified
Multiple Choice
A) If the IRR exceeds the required return, the profitability index will be less than 1.0.
B) The profitability index will be greater than 1.0 when the net present value is negative.
C) When the internal rate of return is greater than the required return, the net present value is positive.
D) Projects with conventional cash flows have multiple internal rates of return.
E) If two projects are mutually exclusive, you should select the project with the shortest payback period.
Correct Answer
verified
Multiple Choice
A) Project A; because it pays back faster
B) Project A; because it has the higher profitability index
C) Project B; because it has the higher profitability index
D) Project B; because it has the higher net present value
E) Project A; because it has the higher net present value
Correct Answer
verified
Multiple Choice
A) -$425.91
B) -$131.83
C) -$383.01
D) $10.45
E) $229.50
Correct Answer
verified
Multiple Choice
A) 18.29 percent
B) 18.38 percent
C) 15.67 percent
D) 17.29 percent
E) 16.67 percent
Correct Answer
verified
Multiple Choice
A) 9.08 percent
B) 9.16 percent
C) 9.58 percent
D) 9.23 percent
E) 9.19 percent
Correct Answer
verified
Multiple Choice
A) 15.48 percent
B) 17.76 percent
C) 18.09 percent
D) 22.68 percent
E) 18.53 percent
Correct Answer
verified
Multiple Choice
A) 14.69 percent
B) 14.14 percent
C) 15.03 percent
D) 15.28 percent
E) 14.21 percent
Correct Answer
verified
Multiple Choice
A) A long-term capital-intensive project
B) Two mutually exclusive projects
C) A proposed expansion of a firm's current operations
D) Different-sized projects
E) Investment funds available only for a limited period of time
Correct Answer
verified
Multiple Choice
A) The net present value is a measure of profits expressed in today's dollars.
B) The net present value is positive when the required return exceeds the internal rate of return.
C) If the initial cost of a project is increased, the net present value of that project will also increase.
D) If the internal rate of return equals the required return, the net present value will equal zero.
E) Net present value is equal to an investment's cash inflows discounted to today's dollars.
Correct Answer
verified
Multiple Choice
A) 9.43 percent
B) 8.29 percent
C) 7.81 percent
D) 8.42 percent
E) 7.55 percent
Correct Answer
verified
Multiple Choice
A) Mutually exclusive
B) Conventional
C) Multiple choice
D) Dual return
E) Crosswise
Correct Answer
verified
Multiple Choice
A) Project A, because it pays back faster
B) Project A, because it has the higher internal rate of return
C) Project B, because it has the higher internal rate of return
D) Project A, because it has the higher net present value
E) Project B, because it has the higher net present value
Correct Answer
verified
Showing 41 - 60 of 109
Related Exams